Council approves bid for Pines and Mission project

 

Last updated 7/13/2023 at 1:43pm



SPOKANE VALLEY — The Council voted unanimously to award funds to N.A.

Degerstrom, Inc. for the Pines and Mission Intersection Improvement Project at its regular meeting on July 11.

The total estimated cost of the project will be $2,207,550 and is broken down by category. Preliminary engineering expenses are $351,650, and developer contributions will be $117,507.

Right-of-way construction costs will be $134,000, with other construction costs running $1,721,900.

The project will add a southbound right-turn lane and provide two eastbound left-turn lanes to the existing intersection at Pines...