Successful tests mean upgrades for new well

 


At its Monday, Feb. 4 meeting, the Airway Heights City Council took a peek at the future, with items like its reclaim water well and planned multi-use building.

One of the larger items on the agenda was a change order for the city’s recovery well, totaling an additional $234,062.57 for the project. The change comes from an unexpected increase in capacity for the well, based on initial pumping test results that took place a few months ago.

The change order increases the total contract’s working time by 30 days, making it a total of 80 days of work. The total project contract price is $...